Title: Approval of Cape Seal roadway pavement treatment on Cypress Ave, Eastleigh Dr, Osceola Rd, and Varona St Summary: Staff is seeking Commission approval to piggy back on Polk County 2015 Annual Pavement Management Alternative Methods #15-601. Polk County has awarded this contract to Asphalt Paving Systems through October, 2018. The contract includes leveling asphalt, chip sealant, micro paving, and striping. Based on the unit prices of the contract, the total expenditure for the project is $86,984.60.
Attachments: 1. Polk Cnty Contract Bid #15-601, 2. Polk Cnty Contract bid item list 022717, 3. T Belleair - Cape Level - Var Sts - $87K -- 2-7-17 (2)

Summary

To: Mayor Gary H. Katica, Commissioners

From: Keith A. Bodeker

Date: 2/27/2017

______________________________________________________________________

Subject:

Title

Approval of Cape Seal roadway pavement treatment on Cypress Ave, Eastleigh Dr, Osceola Rd, and Varona St

 

Summary:

Staff is seeking Commission approval to piggy back on Polk County 2015 Annual Pavement Management Alternative Methods #15-601.  Polk County has awarded this contract to Asphalt Paving Systems through October, 2018.  The contract includes leveling asphalt, chip sealant, micro paving, and striping. Based on the unit prices of the contract, the total expenditure for the project is $86,984.60.

End

Body

Previous Commission Action: N/A

 

Background/Problem Discussion: The current condition of the asphalt on Cypress Ave, Eastleigh Dr, Osceola Rd (from Indian Rocks Road east to Varona St.), and Varona St (from Osceola north Ponce De Leon Blvd) is in need of repair and treatment to help extend the life of the current roadway.  Staff is planning on filling all open potholes with leveling asphalt, then applying a chip seal application over top of it to help seal the current asphalt.  Immediately after the chip seal is applied a top coat of micro pave will be applied to the roadway with necessary striping to follow short after.  The town is planning work on Osceola and Varona in the future, and this work should allow the road condition to stabilize until that project occurs. 

 

Expenditure Challenges  N/A

 

Financial Implications:  The total expenditure for the project is $86,894.60.

 

Recommendation:  Staff recommends the Commission move approval of piggybacking the Polk County contract #15-601 and Asphalt Paving Systems to install Cape Seal roadway pavement treatment to Cypress Ave, Eastleigh Dr, Osceola Rd, and Varona St  to  in the amount of $86,894.60.

 