Summary
To: Mayor and Commissioners
From: JP Murphy
Date: 6/11/2018
______________________________________________________________________
Subject:
Title
Variance Request #1-Maintenance Facility Structure
Summary:
Please refer to staff report/presentation item #18-0179 for additional details.
Variance to the Town of Belleair Code of Ordinances, Subpart B, Land Development Code, Article II, Zoning Districts, Section 74-84, to locate a maintenance facility structure within the required 25-foot setback, 2-feet from the property line.
The applicant is proposing to construct a 3,300 square foot metal maintenance facility and parking area on the northeast corner of the golf course property. The proposed location of this structure will be 2-feet from the property line. Section 74-84 of the Town Code specifies that the structure shall be setback 25-feet from the property line. Adjacent to this proposed facility is public property that is also used by the Town as their Public Works building, which is compatible with the applicant’s proposed use. In addition, the applicant proposes to relocate the existing fuel storage tanks to facilitate this overall construction. Staff has not reviewed the proposed location of these tanks, which shall comply with all pertinent state and local regulations.
The applicant is requesting a variance of 23-feet from the required 25-foot setback requirement. Please refer to the justification contained in the variance application and Phase 3 narrative.
Planning and Zoning Board approved unanimously.
End
Body
Previous Commission Action: N/A
Background/Problem Discussion: N/A
Expenditure Challenges N/A
Financial Implications: N/A
Recommendation: N/A
Proposed Motion Move to approve/deny variance request #1, allowing for the construction of a maintenance facility structure to encroach 23 feet in to the required 25 foot setback.