Summary
To: Mayor and Commissioners
From: Gay Lancaster, Town Manager
Date: 11/6/2023
______________________________________________________________________
Subject:
Title
Award of PW23-10: Carl and Shirley Avenue Improvements
Summary:
Town staff received three bids and is recommending the award to the lowest bidder.End
Body
Previous Commission Action: Discussion of Carl and Shirley Avenue infrastructure project.
Background/Problem Discussion: As part of the Capital Improvement Plan (CIP), staff solicited bids for road, drainage, and pedestrian improvements to Carl & Shirley Avenues. The scope of this project consist of construction of roadway, drainage and pedestrian improvements along Carl Avenue from The Mall to Barbara Circle and Shirley Avenue from Ponce de Leon Boulevard to Carl Avenue The town received three bids, with the lowest bid at $2,450,028.00. Staff has reviewed the information submitted and is requesting that the contract be awarded to Evolution Contracting, LLC, the lowest bidder. A recommendation of award and the plans for the project area are enclosed for your review.
Recommendation: Award of contract PW 23-10 Carl and Shirley Avenue Improvements to Evolution Contracting, LLC, in the amount of two million, four fifty thousand, twenty-eight dollars ($2,450,028.00).
Proposed Motion: I move to award contract PW 23-10 Carl and Shirley Avenue Improvements to Evolution Contracting, LLC, in the amount of two million, four fifty thousand, twenty-eight dollars ($2,450,028.00).