Title: 2021-2022 Budget Discussion: Capital Equipment and Infrastructure Plan Summary: This is the presentation of the Capital Equipment and Infrastructure funds, with recently updated equipment and vehicles that have been added over the 2020-2021 budget year.
Attachments: 1. CIP - 21-22.pdf, 2. Capital Equipment Replacement Fund, 3. 2021-2022 Departmental Expenditures (3)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Summary

To: Town Commission

From: Ashley L. A. Bernal

Date: 8/17/2021

______________________________________________________________________

Subject:

Title

2021-2022 Budget Discussion: Capital Equipment and Infrastructure Plan

 

Summary:

This is the presentation of the Capital Equipment and Infrastructure funds, with recently updated equipment and vehicles that have been added over the 2020-2021 budget year.

Body

 

Previous Commission Action: Discussion of General and Enterprise funds, as well as pay and compensation study which impacted personnel costs.

 

Background/Problem Discussion: The Capital Equipment Replacement Fund retains capital set aside for the General Fund. Equipment and vehicles are depreciated using a salvage added, straight line methodology. Each department is responsible for funding this depreciation by way of capital transfer to the Capital Equipment Replacement Fund (CERF;301). Attached to this item is a description of each department’s equipment and vehicular transfer schedules. At a high level, here are the transfers to Fund 301 for the General Fund:

 

Department

Amount

Administration

$7,203

Support Services

$28,866

Police

95,328

Public Works

$48,877

Recreation

$34,060

Total

$214,334

 

Additionally, the Capital Improvement Master Plan has been attached to this item. Listed below are the projects proposed for 2021-2022 update with Approved Master Plan Estimates:

                     Carl Avenue with Shirley addition - $11,960,125

                     Pinellas Road Final: $3,072,752

                     Bayview Bridge to Indian Rocks Road Engineering - $163,200

                     Indian Rocks Road (Mehlenbacher to Poinsettia) Engineering & Construction - $2,951,102

                     Bluff Study - $135,000

                     Belleair Creek (Ponce to Bridge) Study - $78,000

                     Ponce de Leon Blvd (Roundabout to Trail) - $153,000

                     Bridge Repairs (Winston and North Pine) - $97,000

                     Seawall Repairs - $260,000

 

The Capital Improvement Master Plan contains outlay for future projects and timelines through 2024-2025.

 

 

Expenditure Challenges:  The capital equipment expenditures have been updated in the General Fund budget, which will be reflected at the first hearing in September.

 

Recommendation:  No recommendation is needed, this item is only for discussion.

 

Proposed Motion:  No motion is needed, this item is only for discussion.