Title: Final Bluff Report Summary: After two years, APTIM has completed the study of the bluff. The attached report includes data on the bluff and environmental impacts, possible solutions for preserving the bluff, and recommendations on what will be the best direction. Staff will be presenting a high-level summary, with Dr. Danchuk from APTIM available for questions, and is requesting the board's concurrence with the engineer's recommendation of 3B.
Attachments: 1. Task 5_Final Report_DistrictCommentResponses_06252025

Summary

To: Infrastructure Board

From: Gay Lancaster, Town Manager

Date: 8/18/2025

______________________________________________________________________

Subject:

Title

Final Bluff Report

 

Summary:

After two years, APTIM has completed the study of the bluff. The attached report includes data on the bluff and environmental impacts, possible solutions for preserving the bluff, and recommendations on what will be the best direction.

 

Staff will be presenting a high-level summary, with Dr. Danchuk from APTIM available for questions, and is requesting the board’s concurrence with the engineer’s recommendation of 3B.

End

Body

Recommendation: Staff recommends pursuing option 3B for the preservation of the bluff.

 

Proposed Motion: I move to confirm recommending option ________ for Commission approval.