Summary
To: Infrastructure Board
From: Ashley Bernal, via Gay Lancaster, Town Manager
Date: 8/12/2024
______________________________________________________________________
Subject:
Title
Current Project Updates
Summary: Several projects which began in 2023-2024 are nearing completion. This item serves as an update on current work and outlook for projects anticipated in the future.
End
Body
Previous Commission Action: Approval of contracts and 2023-2024 budget.
Background/Problem Discussion: The biggest project underway is the Carl/Shirley Avenue project. It was originally estimated at $2.1 million and the low bid was returned at $2.4 million. It includes full roadway reconstruction, installation of sidewalks, drainage improvements, and streetlighting. This project began in March 2024 and is expected to be completed in November 2024.
The Bluff Study is continuing on schedule. It is a 50/50 funded project with the Southwest Florida Water Management District (SWFWMD) at $130,000 each, for a total cost of $270,000. Staff has included the most recent quarterly report submitted to SWFWMD as an update to the project's progress, which is expected to be completed in December 2024.
Engineering and Design work for Indian Rocks Road Phase 3 (Bayview Drive to Belleview Boulevard) is ongoing. Due to the historical significance of the bridge, which was originally constructed in 1927, the State Historical Preservation Office (SHPO) is now involved in the project. Staff recently engaged in a discussion with RS&H (the project's Engineer of Record EOR), our Consultant Engineer, and SHPO to discuss the next steps. The Town will coordinate a meeting for all stakeholders to review the plans for the bridge, discuss ways of honoring its history, and then move forward to complete Phase 3 planning. This project is set for construction in 2025-2026. Including the 1.1 million allocation for Phase I, the Town has secured $5.2 million through Legislative appropriations. The most r...
Click here for full text